Three Park Place IDA Fitout (Dublin, Ireland)
Mechanical Services Installation – fit-out 3rd, 6th, 7th & 8th floor retrofit
Project Summary
- Strip out all existing HVAC services and installation of new fully coordinated mechanical
- Remove and store 121no existing FCU’s & reinstall with 48no new FCU’s to revised HVAC installation
- LEED Platinum project
- Insulated Fire duct installation to BS 476 part 24 standards
- Trend BMS system
- 2no comms rooms
- Comms room with EN 15004-1:2008 Gaseous Fire Extinguishing Systems c/w smoke fire damper system installation
Project Consultants | Varming engineers |
Main Contractor | Sisks |
Project Start Date | Finish Date | Fit-out Value  | Lynskey Project Manager |
January 2019 | August 2019 | €2m | Terry O’Rourke |