Kerrygold, Mitchelstwon, Cork, Ireland
Extension to Kerrygold Park, Mitchelstown, Co. Cork
Project Summary
- Production systems including MTHW, LGHW, Chilled water and Domestic water systems
- Mixture of stainless steels and carbon pipework
- Installation of MTHW boiler and system operating at 115degees flow
- Production AHU units with automatic adjustable grill vanes to suit both warm and cooling air to suit production area with ceiling heights of 8metres
- Compressed air system
- Office space including heat recovery units (fresh air systems) FCU, Fire dampers, VCDs, radiators, water supply ect
- Installation of unit heaters, de strat fans and roof mounted fans for warehouse and cold store units.
- Carried out a survey of existing services and coordinated new services (plant, pipework, ductwork) to suit existing without effecting production time
- 3d coordination of new production, warehouse and office area,
Project Consultants | Varming Consultant Engineers |
Main Contractor | Flynns MC |
Project Start Date | Finish Date | Fit-out Value  | Lynskey Project Manager |
Nov-21 | Feb 2023 | € 2 m | Thomas Clarke |